Set an interim plan. Click the Project smyrnamusiclessons.com the Schedule group, point to Set Baseline, and then click Set Baseline.. Click Set interim plan.. In the Copy box, click the start and finish or baseline values that you want to save. (The current start and finish, and baseline values are not numbered.) In the Into box, click the name of the interim plan into which you want to copy the . Set a baseline for your project. Open your project for editing. Go to Schedule in the Quick Launch, then on the Task tab, in the Editing group, click Set Baseline, and then click the numbered baseline you want to use for the current project data. You can save up to 11 different baseline data sets, including the unnumbered Baseline.